Exoscale status

Router upgrade on DK2 data center from 2016.03.02 8PM to 2016.03.03 5AM CET

One of our upstreams is upgrading its router. The traffic will be transparently switched to other upstreams during the operation. No impact is planned.

completed

Network maintenance window for DK2 datacenter is now closed. No impact was observed.

in-progress

The network maintenance window is now open. Network flows for DK2 datacenter have been rerouted.